APPENDIX
– 14-I-E
(FORMAT FOR LETTER OF PERMISSION)
OFFICE OF DEVELOPMENT COMMISSIONER/
-------------SPECIAL ECONOMIC ZONE
DEPARTMENT OF COMMERCE, GOVERNMENT OF INDIA
Dated
the-----------------------------
To,
M/S -----------------------
-----------------------
Subject: Your unit application for
permission under the EOU/SEZ Scheme for ________________________________ No.------------------SEZ
-------------- dated-----------
Dear Sir/Madam,
With reference
to the above mentioned application, Govt./Development Commissioner is pleased
to extend to you all the facilities and privileges admissible and subject to
the provisions as envisaged in EOU/SEZ Scheme 2004-2009 for the establishment
of a new undertaking at__________ in the State of ____________________for the
following items(s) up to the capacities specified below on the basis of maximum
utilisation of plant and machinery: -
Item(s) of production Annual
capacity
The above
permission is subject to the conditions stipulated in Annexure in
addition to the following conditions: -
(i) The unit shall export its entire
production/service, excluding rejects and sales in the domestic tariff area as
per provisions of EOU/SEZ Scheme for a period of 5 years from the date of
commencement of production. For this
purpose the unit shall furnish the requisite legal undertaking as prescribed in
the EOU/SEZ Scheme to the Development Commissioner concerned. Before signing
the LUT it should have its own
permanent E-mail address. The
unit would have the option to renew its EOU/SEZ status or opt out of the scheme
as per industrial policy in force at that time in relation to items of
production.
(ii) The unit would be
required to achieve positive Net Foreign Exchange (NFE) as prescribed in the
EOU/SEZ Scheme for a period of five years from the date of commencement of
production, failing which it would be liable for penal action.
(iii) It is noted that you require imported
Capital Goods valued at Rs.---------for the proposed project.
iv) Import/local purchase of all items
except those listed in prohibited list for import/export will be permitted.
v) Possession of
allotted plot/SDF will be taken within a period of 3 months of issue of
approval letter and construction of the factory building/implementation of
project shall be started within next six months (in case of SEZ units only).
(vi) This Letter of Permission is valid
for 3 years from its date of issue with in which you should implement the
project and commence production and would automatically lapse if an application
for the extension of validity is not made before the end of the said period.
Date of commencement of production shall be intimated to the Development
Commissioner of concerned SEZ.
(vii) The approval is based on the details
furnished by you in your project application.
(viii) You shall be required to enter into a
Legal Agreement in the prescribed form (Appendix 14-IF) with DC_______ for
fulfilling the terms and conditions mentioned in the LOP.
(ix) You are requested to confirm acceptance
of the above terms and condition to the undersigned within 45 days.
(x) If you fail to comply with the
conditions stipulated above, this letter of approval is liable for
cancellation/revocation.
(xi) All future correspondence for
amendments/changes in terms and conditions of the approval letter or for
extension of its validity if required, etc. may be addressed to the
undersigned.
Yours
faithfully,
Development
Commissioner
---------------------SEZ
Copy forwarded to :-
1. Deputy
Commissioner/Central Excise/Customs/I/C of EOU (for EOUs)
2. Asstt
Commissioner/Deputy Commissioner (Custom)…………… SEZ (for SEZ Units)
3. Director of Industries, Govt. of (State)
4. Development Commissioner(SSI),Nirman
Bhavan,New Delhi.
Development Commissioner
------------------