PM to hold roadshow in Puri on MondayViolations of economic sanctions: Criminal penalties come into forceBengaluru Customs nabs 4 pax with gold powder worth Rs 1.96 CroreKejriwal’s assistant put in police custody for 5 days in Swati Maliwal caseAllahabad HC upholds decision to dismiss judicial officer demanding dowryNawaz Sharif alleges former Chief Justice plotted to oust him as PM in 2017Heavy downpours claim 50 lives in Central AfghanistanSoaring funeral costs compelling people to let go bodies unclaimed in Canada9 pilgrims burnt to death as bus catches fire near Nuh in HaryanaSpain denies dock permission to Indian ship carrying arms to Israel12 Unicorns, over 125 startups commit to onboarding ONDCBEML secures Rs 250 crore order from Northern Coal FieldsBharat Parv celebration takes centerstage at Cannes Film FestivalSteel industry should work towards reducing emissions: Steel SecretaryI-T - Additions framed on account of unexplained cash credit & unexplained money, are not tenable where cash deposits & withdrawals were of personal funds & were done through banking channels: ITATUS says not too many vibrant democracies in the world than IndiaI-T - Benefit of section 11(2) can not be denied merely on reasoning that form 10 is filed belatedly: ITATIndia says Chabahar Port to benefit Central Asia and AfghanistanRussia seizes Italy’s UniCredit assets worth USD 463 mnCus - Order re-determining transaction value based on CRCL test report is not correct & hence unsustainable: CESTATCus - If price is not sole consideration for sale, then transaction value can be rejected under Rule 8 of Export Valuation Rules & then must be redetermined sequentially through Rules 4 to 6: CESTATSC upholds ICAI rules capping number of audits per year
 
Govt focuses on 215 large but stuck projects involving funds of Rs 7 lakh crore

By TIOL News Service

NEW DELHI, JUNE 13, 2013: WHILE speaking to the mediapersons today, the Finance Minister, Mr P Chidambaram, said that the Govt has identified as many as 215 large projects in the public as well as private sectors, involving funds to the tune of Rs seven lakh crores, and these projects are stuck at some stage of completion.

The FM said that the time and cost overruns being faced by these projects has also been documented, as well as the action required to remove the implementation bottlenecks. While some of bottlenecks being faced are in the domain of regulatory authorities at the Central level, a large number of impediments are those that lie in the domain of State Governments, and local bodies. He therefore flagged the need for having an institutional mechanism which has sufficient authority, to coordinate with the concerned authorities and get these projects moving on the ground.

On this occasion, Mr Anand Sharma, Commerce Minister, stated that his Ministry has done a compilation of projects in the manufacturing sector, which are stalled due to various inter-agency bottlenecks. He also emphasized the need to sensitize the State Governments in order to elicit their cooperation.

Ms Jayanthi Natarajan, Minister of Environment & Forests, stated that her Ministry has an on-line portal where the status of all projects which have been submitted for clearances with the Ministry, could be tracked. She further stated that pendency of projects for various Environment and Forest clearances has now been significantly reduced, and the process to accord such clearances has been further streamlined.

Deputy Chairman, Planning Commission, was of the opinion that this proposed institutional mechanism should be put in place at the earliest, and 20 -30 major projects chosen across the sectors on priority, for speedy resolution. This will work as a confidence booster to investment sentiment and signal the government's seriousness on the issue, he said.

Principal Secretary to Prime Minister apprised that a list of projects of the public sector from various Ministries such as Coal, Power, and Shipping has already been compiled. FICCI has also submitted a list of 52 projects in the private sector, with an investment greater than Rs.1000 crore, which are delayed due to various bottlenecks. He was of the opinion that the monitoring mechanism may be anchored in the Cabinet Committee on Infrastructure, with a supportive cell, suitably empowered, which brings these projects to the CCI, and also follow up on the decisions of the CCI.

The Cabinet Secretary stated that the Ministries dealing with such stalled projects will need to monitor the projects closely and instructions have already been issued in this regard on 16.1.2013. He apprised that the Cabinet Secretariat has prepared an `Online CCI Projects Tracking System` portal for tracking projects of over Rs.1000 crore. The Cabinet Secretary presented snap shots of the tracking system available on the Cabinet Secretariat Website. Secretary, DEA invited attention to the fact that very often, stalled projects are in the private sector or in sectors not in the infrastructure domain, e.g., in the cement industry.

 


POST YOUR COMMENTS
   

TIOL Tube Latest

Shri N K Singh, recipient of TIOL FISCAL HERITAGE AWARD 2023, delivering his acceptance speech at Fiscal Awards event held on April 6, 2024 at Taj Mahal Hotel, New Delhi.


Shri Ram Nath Kovind, Hon'ble 14th President of India, addressing the gathering at TIOL Special Awards event.