PM to hold roadshow in Puri on MondayViolations of economic sanctions: Criminal penalties come into forceBengaluru Customs nabs 4 pax with gold powder worth Rs 1.96 CroreKejriwal’s assistant put in police custody for 5 days in Swati Maliwal caseAllahabad HC upholds decision to dismiss judicial officer demanding dowryNawaz Sharif alleges former Chief Justice plotted to oust him as PM in 2017Heavy downpours claim 50 lives in Central AfghanistanSoaring funeral costs compelling people to let go bodies unclaimed in Canada9 pilgrims burnt to death as bus catches fire near Nuh in HaryanaSpain denies dock permission to Indian ship carrying arms to Israel12 Unicorns, over 125 startups commit to onboarding ONDCBEML secures Rs 250 crore order from Northern Coal FieldsBharat Parv celebration takes centerstage at Cannes Film FestivalSteel industry should work towards reducing emissions: Steel SecretaryI-T - Additions framed on account of unexplained cash credit & unexplained money, are not tenable where cash deposits & withdrawals were of personal funds & were done through banking channels: ITATUS says not too many vibrant democracies in the world than IndiaI-T - Benefit of section 11(2) can not be denied merely on reasoning that form 10 is filed belatedly: ITATIndia says Chabahar Port to benefit Central Asia and AfghanistanRussia seizes Italy’s UniCredit assets worth USD 463 mnCus - Order re-determining transaction value based on CRCL test report is not correct & hence unsustainable: CESTATCus - If price is not sole consideration for sale, then transaction value can be rejected under Rule 8 of Export Valuation Rules & then must be redetermined sequentially through Rules 4 to 6: CESTATSC upholds ICAI rules capping number of audits per year
 
I-T - No builder or developer can be penalized for delay attributed to Competent Authorities in issuing completion certificate: HC

By TIOL News Service

MUMBAI, JAN 29, 2019: THE ISSUE BEFORE THE DIVISION BENCH IS - Whether when the project was completed within time and application for grant of certificate was also made well within time, then the builder should not suffer on account of delay at hands of Competent Authority issuing the certificate. YES IS THE VERDICT.

Facts of the case:

The Assessee is a builder/developer. For the subject A.Y, the assessee filed its return declaring income as 'Nil', after claiming deduction u/s 80IB(10) in respect of its development project. The returned income was also assessed u/s 143(3) at NIL. Later on, the AO issued a notice u/s 148, seeking to reopen the assessment, on the ground that the commencement certificate for the project in respect of which benefit of Section 80IB(10) as claimed, was received on Jan 19, 2005 whereas the Occupation Certificate was not obtained till Mar 31, 2009. Thus, disentitling the assessee to the benefit of Section 80IB(10). Thus, the assessee's income was determined at Rs.6.35 Crores.

On appeal, the CIT(A) held that the assessee was entitled to the benefit of Section 80IB(10) as the delay in issuing the occupancy certificate was on account of the time taken by the competent authority to issue the certificate when the Applicant had submitted all necessary documents for the issuance of certificate much before the expiry of four years from the end of the financial year in which commencement certificate was obtained. On further appeal, the Tribunal concurred with the opinion of CIT(A) and concluded that the assessee builder could not be penalized for the delay by the Competent Authorities in issuing the completion certificate.

High Court held:

++ the present issue is no longer res integra as it stands concluded against the Revenue and in favour of the assessee by the decision of this Court in CIT v/s. Hindustan Samuh Awas Ltd.. In the said case, it has been held that whether the project is completed within the time framed provided u/s 80IB(10), and an application for issuance of completion certificate is filed within time, then delay on account of the competent authority in issuing completion certificate would not deprive the Assessee, the benefit of Section 80IB(10). To the same effect the decision of the Gujarat High Court in CIT v/s. Tarnetar Corporation. In the present case on facts, it is found that not only the project was completed within time and an application for granting of certificate was also made well within the time. Thus, the assessee should not suffer on account of the delay at the hands of the Competent Authority issuing the certificate.

(See 2019-TIOL-229-HC-MUM-IT)


POST YOUR COMMENTS
   

TIOL Tube Latest

Shri N K Singh, recipient of TIOL FISCAL HERITAGE AWARD 2023, delivering his acceptance speech at Fiscal Awards event held on April 6, 2024 at Taj Mahal Hotel, New Delhi.


Shri Ram Nath Kovind, Hon'ble 14th President of India, addressing the gathering at TIOL Special Awards event.