IndiGo orders 30 Airbus A350s for long haulsFiling of Form 10A & 10AB: CBDT extends due date to June 30RBI to issue fresh guidelines for banks to freeze suspected bank accounts being used for cyber crimesCPGRAMS recognized as best practice in Commonwealth Secretaries of public serviceIsrael-Iran War: A close shave for Global Economy but for how long?KABIL, CSIR ink MoU for Advancing Geophysical InvestigationsI-T - If income from stock-in-trade are held as investments, then provisions of section 14A would apply to such income: ITATTRAI recommends on Infra Sharing, Spectrum Sharing & Spectrum LeasingI-T- Revisionary powers u/s 263 can't be exercised when AO has neither assumed facts incorrectly nor there is incorrect application of law : ITATTechnology Board okays funding of Dhruva Space's Solar Array ProjectI-T- Issue of interest is debatable issue on which two views are possible and AO accepted one of views for which PCIT cannot assume revisional jurisdiction: ITATHealth Secy visits Bilthoven Biologicals, discusses production of Polio VaccineI-T - Estimation of profit element from purchases should be done reasonably if assessee could not conclusively prove that purchases made are from parties as claimed, in absence of confirmations from them: ITATStudy finds Coca-Cola accounts for 11% of branded plastic pollution worldwideI-T- Triplex flats purchased are interconnected and can be considered as 'a residential unit'' as per definition of section 54F of Act : ITATDelhi HC says conspiracy against PM is a crime against StateI-T- AO omitted to probe issue of cash payments made over specified limit; revisionary power u/s 263 is rightly exercised: ITATBrazil makes new rules to streamline consumption taxesI-T-Power of revision unnecessarily exercised where AO had no scope to examine creditworthiness & genuineness of assessee's creditors: ITATBiden signs rules mandating airlines to give automatic refunds for delayed or cancelled flightsI-T-As per settled law, in absence of enabling powers, no disallowance can be made : ITATBYD trying to redefine luxury for new EV variantsGST - On the one hand, the order states registration is liable to be cancelled retrospectively and on the other hand mentions that there are no dues - Order modified: HCSC asks EC to submit more info on reliability of EVMsRight to Sleep - A Legal lullaby
 
PM to launch 60MW Tuirial Hydro Power Project tomorrow

By TIOL News Service

NEW DELHI, DEC 15, 2017: Prime Minister Narendra Modi will formally dedicate the 60 MW Tuirial Hydro Electric Power Project (HEPP) to the Nation. The Prime Minister will also launch ‘MyDoNER App' and will distribute cheques to the Start-up Entrepreneurs Aizawl tomorrow.

The Tuirial HEPP has been constructed as a Central Sector Project and implemented by North Eastern Electric Power Corporation (NEEPCO), under the administrative control of the Ministry of Power, Government of India.

The Cabinet Committee on Economic Affairs (CCEA) cleared the Project for implementation in July 1998 with commissioning scheduled in July 2006. After completion of about 30% of the project activities, the works were totally suspended w.e.f. June 2004 due to local agitation. With sustained efforts by NEEPCO and with active support of Ministry of Power and Ministry of DoNER, Government of India and Government of Mizoram, the stalled works of the project were resumed in January 2011.

The Project being remotely located, encountered various hindrances ranging from inadequate communication infrastructure to the project site, massive failure of the Power House slopes due to poor soil condition, lack of availability of skilled manpower etc. These factors resulted in comparatively longer gestation period for the project. However, with all efforts from the agencies concerned, the project works were completed successfully, leading to commissioning of Unit-I on 25-08-2017 and Unit-II on 28-11-2017.

The project has been implemented by NEEPCO by engaging M/S Bharat Heavy Electricals Ltd for supply and erection of power generating equipment, M/S Patel Engineering Ltd for execution of major civil works and M/S Sew-PES-Tuirial consortium for Hydro-Mechanical works. The Project has been built at a cost of Rs.1302 crore.

The Project is the biggest power project located in the State of Mizoram and will feed the entire energy to be generated to the home State, which will facilitate all-round development of the State and achieving Government of India's ambitious and flagship Mission ‘24x7 Affordable Clean Power for All'.

The State's current demand of electricity is only 87 MW and this is being met by State's mini power projects and availability of its share of power from central sector projects. With the additional 60 MW of electricity from the project, the State of Mizoram will now be the third power-surplus State in North East India after Sikkim and Tripura. Apart from attaining self-sufficiency in electric power, the project will fetch other spin-off benefits to the State of Mizoram like employment generation, navigation, water supply, pisciculture and wild life conservation, tourism etc.


POST YOUR COMMENTS
   

TIOL Tube Latest

Shri N K Singh, recipient of TIOL FISCAL HERITAGE AWARD 2023, delivering his acceptance speech at Fiscal Awards event held on April 6, 2024 at Taj Mahal Hotel, New Delhi.


Shri Ram Nath Kovind, Hon'ble 14th President of India, addressing the gathering at TIOL Special Awards event.