IndiGo orders 30 Airbus A350s for long haulsFiling of Form 10A & 10AB: CBDT extends due date to June 30RBI to issue fresh guidelines for banks to freeze suspected bank accounts being used for cyber crimesCPGRAMS recognized as best practice in Commonwealth Secretaries of public serviceIsrael-Iran War: A close shave for Global Economy but for how long?KABIL, CSIR ink MoU for Advancing Geophysical InvestigationsI-T - If income from stock-in-trade are held as investments, then provisions of section 14A would apply to such income: ITATTRAI recommends on Infra Sharing, Spectrum Sharing & Spectrum LeasingI-T- Revisionary powers u/s 263 can't be exercised when AO has neither assumed facts incorrectly nor there is incorrect application of law : ITATTechnology Board okays funding of Dhruva Space's Solar Array ProjectI-T- Issue of interest is debatable issue on which two views are possible and AO accepted one of views for which PCIT cannot assume revisional jurisdiction: ITATHealth Secy visits Bilthoven Biologicals, discusses production of Polio VaccineI-T - Estimation of profit element from purchases should be done reasonably if assessee could not conclusively prove that purchases made are from parties as claimed, in absence of confirmations from them: ITATStudy finds Coca-Cola accounts for 11% of branded plastic pollution worldwideI-T- Triplex flats purchased are interconnected and can be considered as 'a residential unit'' as per definition of section 54F of Act : ITATDelhi HC says conspiracy against PM is a crime against StateI-T- AO omitted to probe issue of cash payments made over specified limit; revisionary power u/s 263 is rightly exercised: ITATBrazil makes new rules to streamline consumption taxesI-T-Power of revision unnecessarily exercised where AO had no scope to examine creditworthiness & genuineness of assessee's creditors: ITATBiden signs rules mandating airlines to give automatic refunds for delayed or cancelled flightsI-T-As per settled law, in absence of enabling powers, no disallowance can be made : ITATBYD trying to redefine luxury for new EV variantsGST - On the one hand, the order states registration is liable to be cancelled retrospectively and on the other hand mentions that there are no dues - Order modified: HCSC asks EC to submit more info on reliability of EVMsRight to Sleep - A Legal lullaby
 
Cabinet approves Haldia-Varanasi stretch of National Waterway-1

By TIOL News Service

NEW DELHI, JAN 03, 2018: THE Cabinet Committee on Economic Affairs, has given its approval for implementation of the Jal Marg Vikas Project (JMVP) for capacity augmentation of navigation on National Waterway-1 (NW-1) at a cost of Rs 5369.18 crore with the technical assistance and investment support of the World Bank.  The Project is expected to be completed by March, 2023.

Major Impact:

Alternative mode of transport that will be environment friendly and cost effective. The project will contribute in bringing down the logistics cost in the country.

Mammoth Infrastructure development like multi-modal and inter-modal terminals, Roll on - Roll off (Ro-Ro) facilities, ferry services, navigation aids.

Socio-economic impetus; huge employment generation.

No. of beneficiaries :

NW-1 development & operations will lead to direct employment generation to the tune of 46,000 and indirect employment of 84,000 will be generated by vessel construction industry.

States/districts covered

States: Uttar Pradesh, Bihar, Jharkhand, West Bengal

Major Districts:   Varanasi, Ghazipur, Ballia, Buxar, Chhapra, Vaishali, Patna, Begusarai, Khagaria, Munger, Bhagalpur, Sahibganj, Musrhidabad, Pakur, Hoogly, Kolkata.

Project details:

Funding pattern :

IBRD loan component: Rs. 2, 512 crore (US$ 375 million).

Government of India counterpart funds: Rs. 2,556 crore (US$ 380 million), to be sourced from budgetary allocation and proceeds from bond issue.

Private sector participation under PPP mode: Rs. 301 crore (US million).

Major Components :

Fairway Development

Construction of the multi-modal terminal at Varanasi.

Construction of the multi-modal terminal at Sahibganj.

Construction of the multi-modal terminal at Haldia.

Construction of an inter-modal terminal at Kalughat .

Construction of an inter-modal terminal at Ghazipur.

Construction of a new navigation lock at Farakka.

Provision of navigational aids.

Construction of five pairs of Roll on-Roll off (Ro-Ro)  terminals.

Construction of Integrated Ship Repair and Maintenance Complexes.

Provision of River Information System (RIS) and Vessel Traffic Management System (VTMS)

Bank Protection works

Background:

  • One of the major problems for a commercially viable and safe navigation on NW-1 is low depth upstream of Farakka due to low discharges from tributaries and difficult hydro morphological characteristics of river Ganga.
  • A pilot study on the Allahabad-Ghazipur stretch was commissioned by Inland Waterways Authority of India (IWAI) to find solutions to this problem.
  • Based on the findings of this study, a proposal for development of NW-1 at an estimated cost of Rs. 4,200 crore (US$ 700 million) was taken up  for seeking technical assistance and investment support from the World Bank to the tune of US$ 350 million in three Phases.
  • Finance Minister announced JMVP in Budget Speech in July 2014, to enable commercial navigation of at least 1500 tonnes vessels in Ganga.

BACKGROUNDER NOTE

Implementation strategy/ and targets:

  • Fairway development through performance based contract for least assured depth of 2.2 metres to 3 metres and bottom channel width of 45 metres, bank protection works, and provisions of navigation aids.

Funding Pattern:

  • IBRD loan component: Rs. 2, 512 crore (US$ 375 million).
  • Government of India counterpart funds: Rs. 2, 556 crore (US$ 380 million), to be sourced from budgetary allocation and proceeds from bond issue .
  • Private sector participation under PPP mode: Rs. 301 crore (US million) .

Major interventions and their completion timeline:

S.No

Major milestones

Time Frame for completion/ Target date

1.

Fairway Development

March, 2023

2.

Construction of Phase-I of multi-modal terminal at Varanasi.

November, 2018

3.

Construction of Phase-I of the multi-modal terminal at Sahibganj.

March, 2019

4.

Construction of multi-modal terminal at Haldia.

March, 2019

5.

Construction of inter-modal terminal at Kalughat.

March, 2020

6.

Construction of inter-modal terminal at Ghazipur.

March, 2020

7.

Construction of intermodal terminal at Tribeni/Kalyani

March, 2020

8.

Construction of new navigational lock at Farakka.

March, 2019.

9.

Integrated Vessel Repair & Maintenance Complexes

March, 2020

10.

Construction of Ro-Ro jetties

March, 2020

11.

Vessel Procurement

March, 2019

12.

Land Acquisition and R&R/RAP

March,2019

13.

Provision of River Information System (RIS) and Vessel Traffic Management System (VTMS).

March, 2020

14.

Bank protection works.

December, 2019

Details and progress of scheme already running:

Construction of multi-modal terminal at Varanasi:

Contract for construction of Phase-I (A) of the terminal at an estimated cost of Rs.169.59 crore awarded in May, 2016. Physical progress of work: 25%.

Construction of multi-modal terminal at Haldia:

Contract awarded for constructing a Rs 517.36 crore state-of-the-art multi-modal terminal at Haldia, West Bengal. Work initiated.

Construction of multi-modal terminal at Sahibganj:

Contract for construction of phase-I (A) of the terminal at an estimated cost of Rs. 280.90 crore awarded in October, 2016. Physical progress of work: 25.62%

Construction of a new navigation lock at Farakka Barrage :

Contract for construction of a new navigation lock at an estimated cost of Rs 359.19 crore awarded in November, 2016. Physical progress: 22.30%

Least Assured Depth (LAD) :

Tender process for fairway development through Performance Based Maintenance Dredging Contract for Provision of Least Assured Depth and quantity based dredging to provide a depth of 2.2 m to 3 metres between Farakka and Varanasi is being completed for awarding.

Development of Kolkata and Patna terminals under PPP mode :

In order to scale up private investment in the IWT sector, IWAI has identified Kolkata terminal (GR Jetty-1, GR Jetty-II and BISN) and Patna terminal (Gaighat and Kalughat) for their development and operation under the Public-Private-Partnership (PPP) mode.

Construction of Ro-Ro terminals : Locations: Rajmahal and Manikchak;Samdaghat and Manihari;Kahalgaon and Tintanga;Hasnapur and Bakhtiyarpur; and Buxar and Saraikota.

Ferry terminals in six cities :

Contract awarded to a joint venture of Thompson Design Group (TDG), Boston (USA) and Infrastructure Architecture Lab of Massachusetts Institute of Technology (MIT) (USA) in December 2016 for identifying suitable locations for construction of ferry terminals in six cities - Varanasi, Patna, Bhagalpur, Munger, Kolkata and Haldia on NW-1.

Design of inland vessels:

IWAI in August, 2016 signed a contract with M/s DST, Germany to design vessels, especially suited to navigate on NW-1. Consultancy completed with submission of stipulated 13 designs. Designs accepted by the Vetting Committee. Vessel testing is going on.

River Information Services (RIS) on National Waterway -1:

IWAI has taken up a technologically challenging project of setting up of River Information Service System on NW-1 for the first time in India. River Information System (RIS) are equipment, hardware and software information technology (IT) related services designed to optimize traffic and transport processes in inland navigation.


POST YOUR COMMENTS
   

TIOL Tube Latest

Shri N K Singh, recipient of TIOL FISCAL HERITAGE AWARD 2023, delivering his acceptance speech at Fiscal Awards event held on April 6, 2024 at Taj Mahal Hotel, New Delhi.


Shri Ram Nath Kovind, Hon'ble 14th President of India, addressing the gathering at TIOL Special Awards event.