Indigenous Technology Cruise Missile successfully flight-tested by DRDO off the Odisha coastUS imposes fresh sanctions against Iranian drone productionIREDA's GIFT City office to boost Green Hydrogen and Renewable Energy Manufacturing ProjectsVoting for General Elections 2024 commences tomorrowGlobal warming up to 3 degrees to cost 10% of global GDP: StudyNexus between Election Manifesto and Budget 2024 in July!Clearing the Air: Airtel's SC Decision provides clarity on test of AgencyGST implications for Corporate Debtor under IBCI-T- Petitioner's CIBIL score lowered due to same PAN being issued to another assessee who defaulted on loan; I-T Deptt to inform CIBIL of remedial measures taken: HCBrazil’s proposal to tax super-rich globally finds many takers in G20 GroupI-T- Additions framed on account of unconfirmed cash loans upheld in part, where assessee is unable to discharge onus of proving source of cash deposits : ITATCPM manifesto promising annihilation of all weapons of mass destructions including nuclear, draws flak from Defence MinisterI-T- Registration of trust u/s 12A denied due to inadvertent error by assessee in filing Form 10AB but with wrong selection code; case remanded for reconsideration: ITATBiden favours higher steel tariff on ‘cheating’ China + may up tariff on dominant solar tech suppliersI-T- Enhancement of income is not sustainable if CIT (A) not follow sec 251 and no notice given to assessee of enhancement : ITATUS Poll: Biden trumps Trump in money race by USD 75 mnI-T- Assessee is entitled for depreciation on goodwill arising out of difference between cost of acquisition and net value of assets and liabilities as per book value of CAPL : ITATNetanyahu says Israel to decide how and when to respond to Iran’s aggressionI-T- There is no scope of extrapolation in search assessment based solely on assumptions and surmises in absence of any tangible material qua the relevant assessment year: ITATGoogle slays costs by laying off staffers & shifting roles outside USI-T- Re-assessment cannot be sustained where based on borrowed satisfaction & where conducted in a mechanical manner: ITATHeavy downpours drown Dubai; Airport issues travel advisoryCus - There cannot be an exercise of jurisdiction to injunct invocation of BG, as it is a settled principle of law that bank guarantee constitutes an independent contract between the bank and the party in whose favour BG is furnished: HCHM pledges to make India completely Maoist-freeGST - Except for holding that the taxpayer had availed ITC which is blocked credit u/s 17(5), no reasons are specified - Order set aside and matter remanded: HCMicrosoft to inject USD 1.5 bn in AI Group G42 of UAEGST - Injustice would be caused unless petitioner is provided another opportunity to contest tax demand on merits - Subject to deposit of 10% of demand, matter is remanded: HCCanadian budget proposes more taxes on higher income groups & tax credits for EVsWorld leaders appeal for quick ratification of UN Ocean Treaty
 
CCEA approves Zojila tunnel with parallel escape tunnel in J&K

By TIOL News Service

NEW DELHI, JAN 03, 2018: THE Cabinet Committee on Economic Affairs, has given its approval to the construction, operation and maintenance of 2-lane bi-directional Zojila Tunnel with Parallel Escape (Egress) Tunnel excluding approaches on Srinagar-Leh section connecting NH-1A at Km 95.00 and at Km 118.00 in Jammu & Kashmir on Engineering, Procurement and Construction (EPC) mode. The construction of this tunnel will provide all weather connectivity between Srinagar, Kargil and Leh and will bring about all round economic and socio-cultural integration of these regions. The project has strategic and socio-economic importance and shall be an instrument for the development of the economically backward districts in Jammu & Kashmir.

Project Details:

The construction period of the project is seven years which shall be reckoned from the date of commencement of construction.

The civil construction cost of the project is Rs 4899.42 crore.

The total capital cost of the project is Rs 6808.69 crore.  It includes the cost towards Land Acquisition, Resettlement & Rehabilitation and other pre-construction activities as well as Maintenance and Operation cost of tunnel for four years.

The Project aims at construction of 14.150 km long two lane bidirectional single tube tunnel with a parallel 14.200 km long egress tunnel excluding approaches between Baltal & Minamarg in the State of J&K.

The construction of approaches of this tunnel is being undertaken separately.

The project will be implemented by Ministry of Road Transport & Highways (MoRT&H) through National Highways & Infrastructure Development Corporation Limited (NHIDCL).

Impact:

The main objective of the project is to provide all whether connectivity to strategically important Leh region in Jammu & Kashmir which at the moment is limited to at best 6 months because of snow on the passes and threat of avalanches.

This project alongwith other ongoing projects like 6.5 km long Z-Morh tunnel at Gagangir would ensure safe, fast and cheap connectivity between the two regions of Kashmir and Ladakh.

It will further increase the employment potential for the local labourers for the project activities.

The project, on completion, would lead to enormous boost in employment as local businesses get linked to National market and the beautiful region is able to receive round the year tourist traffic.

These sectors will generate employment at multiple levels.


POST YOUR COMMENTS
   

TIOL Tube Latest

Shri N K Singh, recipient of TIOL FISCAL HERITAGE AWARD 2023, delivering his acceptance speech at Fiscal Awards event held on April 6, 2024 at Taj Mahal Hotel, New Delhi.




Shri Ram Nath Kovind, Hon'ble 14th President of India, addressing the gathering at TIOL Special Awards event.