NHAI to go for assessment audit & rank roads for qualityUdhav Govt decides to permit hotels to reopen with 33% capacity from July 8GST - When appeal is provided under statute, writ remedy cannot be invoked by making High Court as middle authority between respondent CTO and appellate authority: HCIndia, China agree to disengage troops in Eastern LadakhGovt denies any move to merge CBDT & CBICNon-payment of consideration within 180 days and ITC reversal in GST (See 'THE INSIGHT' in Taxongo.com)Unlocking of economy - 30% firms operating at 70% capacity utilisation: SurveyCOVID-19 - Global tally spikes to 1.16 Crore with 5.37 lakh deaths + New cases - US inches close to 30 lakhs + 16 lakh in Brazil + India advances close to 7 lakh - third highest in worldKerala Customs seizes gold cargo worth Rs 13 CroreAvailability of ITC in respect of duty/tax paid after July 2017 for past transactions under CEA, 1944/FA, 1994/CA, 1962ST - Assessee collects, processes & stores data of MNREGA beneficiaries on behalf of a State Govt entity - such activity entails discharge of sovereign function & no service tax can be demanded thereon: CESTATTaxability of Trusts and InstitutionsSpike in COIVD-19 cases in Gujarat - Ahmedabad Pr CCIT office hunkers down to provide logistics & other support to patients in DepartmentCX - Valuation - Approach of Revenue by disintegrating the wholesale package and determining the value of individual components under separate provisions of the same Act is not permissible: CESTATCOVID-19 impact on Start-ups - 12% down shutters; 70% adversely hurtCX - Construction service was availed for construction of own manufacturing premises - credit admissible: CESTAT140 in race to develop vaccine for Coronavirus; COVAXIN gets official nodCus - Transaction value of imported goods cannot be rejected without showing any contemporaneous evidence of higher price - charges of undervaluation are unsustainable where no evidence exists to show that assessee & overseas buyers are related parties: CESTATProf Raghavan favours use of CSR funds for R&DReceipt of cash gift through banking channels is per se insufficient to establish creditworthiness of donor or genuineness of such gift: HCProvisions of Section 2(22)(e) cannot be invoked where assessee-company maintains running transactions with its subsidiary: ITATExpenses incurred on repair & annual maintenance of computers are revenue expenses & are eligible for deduction: ITATCOVID-19 - Recovery Rate - Five States report over 80% + 9 States between 70-80 per cent + India’s averages about 60.77 per centGenetic risk score to be reliable tool in diagnosing type-1 diabetes in India
 
200 Rly maintenance projects completed during lockdown

By TIOL News Service

NEW DELHI, JUNE 28, 2020: THE backend warriors of Indian Railways have fully availed the opportunity provided by suspension of passenger services due to pandemic of COVID 19 to successfully executed more than 200 long pending maintenance works including yard remodeling, repair and re-girdering of old  bridges, doubling and electrification of rail lines and  renewal of scissor crossovers. Pending for several years, these unfinished projects often confronted Indian Railways as bottlenecks.

Apart from ensuring supply chains all essential commodities running through parcel trains and freight trains, Indian Railways executed these long pending maintenance works during this lockdown period when passenger services were suspended.

During this period Indian Railways focused on several long pending overdue maintenance works which required traffic block of long durations. These works were pending for several years and were confronting Railways with severe bottlenecks. They were planned during lockdown period considering it ‘Once in a lifetime opportunity' to wipe out these maintenance arrears and take up the execution of work without affecting the train service.

These works taken up for removal of bottlenecks and enhance safety include 82 rebuilding/rehabilitation of bridge, 48 limited height subway/road under bridge in lieu of level crossing gate, 16 construction/strengthening of foot over bridge, 14 dismantling of old foot over bridge, 7 launching of road over bridge, 5 yard remodelling, 1 commissioning of doubling & electrification and 26 other projects.

Some of these key projects are as follows -

Yard Modification work in Jolarpetti (Chennai Division, Southern Railway) was completed on 21st  May 2020.  It resulted in easing out of curve and enhancing the speed up to 60Kmph on Bengaluru end and facilitated Simultaneous reception and dispatch.

Likewise dismantling of old abandoned unsafe Foot Over Bridge at Ludhinana (Firozepur Division, Northern Railway) was completed on 5th May 2020. Dismantling of this 135 meter long old abandoned FOB structure over 19 tracks and 7 passenger platforms was overdue since 2014 after new FOB was commissioned.

Work of re-girdering of bridge on Tunga River (Mysuru Division, South Western Railway) was completed on 3rd May 2020. Dismantling of unsafe deck of Kopar Road ROB near Dombivali (Mumbai Division, Central Railway) was completed on 30rd  April 2020 and it resulting in enhanced safety. This deck was declared unsafe for road users in 2019 and covered 6 railway tracks below.

Two projects of Doubling with Electrification in Varanasi Division, North Eastern Railway were completed on 13th June. One of these projects is Kachhwa Road to Madhosingh Section and the second is 16 km of Manduadih to Prayagraj Section. This resulted in decongestion of east - west routes and facilitation of freight movement. The dismantling work of ROB crossing 8 railway tracks in the approach of Chennai Central Station was completed on 9th May 2020. This ROB was declared unsafe and was closed for heavy vehicles since July 2016. ROB dismantling could not be done as traffic block requirement was very high resulting into massive cancellation /rescheduling of trains with loss of passenger revenue.

Works on construction of two new bridges in Vijayawada Division of South Central Railway were completed on 3rd May. On Howrah- Chennai route, the construction of limited height subway for LC elimination in Khurda Road Division in East Coast Railway was completed on 9th  May 2020 resulting in increased operational efficiency of trains and Safety. Signalling upgradation work of Azamgarh station (Varanasi Division, North Eastern Railway) was completed on 23rd May. Mau - Shahganj section has been upgraded to STD.-II (R), yard speed upgraded from 50 kmph to 110 kmph and simultaneous reception, dispatch and shunting facility provided.

Likewise, renewal of wooden layout Scissors crossover with standard Pre-stress Concrete (PSC) layout in Vijayawada & Kazipet yards (Vijayawada Division, South Central Railway) has been completed. A major block of 72 hrs was taken in Kazipet yard for pending yard remodelling. The old wooden scissors crossover laid in 1970 was replaced with standard PSC layout. Insertion of RCC box at Tilak Nagar station (Mumbai Division, Central Railway) was completed in two mega blocks of 28 hrs and 52 hrs durations on 3rd May. This work was taken up to address the problem of flooding in rainy season near Tilak Nagar station on harbour line.

The innovative pilot project for powering Trains by solar power, developed over a vacant railway land at Bina is under extensive testing. This 1.7 Mega Watt project to directly feed to 25 kV Railway Overhead Line is a joint venture of Indian Railways and BHEL.