Govt annonces Padma Awards - Padma Vibhushan to former Japanese PM Shinzo Abe + S P Balasubramaianm + Dr Belle M Hegde + Sudarshan Sahoo + Padma Bhushan to 10 persons including Tarun Gogoi + Sumitra Mahajan + Nripendra Misra + Ram Vilas Paswan + Keshubahi Patel + Padma Shri to 102 persons of repute26 personnel of CBIC get Presidential Awards; Commissioners C P S Bakshi + G Machunlung + Amitesh Bharat Singh + S Thirunavukkarasu also figure in ListCOVID-19 - Global tally about to touch 10 Crore mark + UK’s death count inches close to 100,000GSI to complete 'ambitious' national-level surveys by 2024GST - Provisional attachment of bank account cannot continue where attachment period u/s 83(2) of the CGST Act has lapsed: HCPresident gives nod to Jeevan Raksha Padak awards for 40 personsGST - Confiscation of goods - High Court cannot intervene at SCN stage - assessee directed to file reply to SCN & appear for hearing: HCGST - Provisional attachment of petitioner's cash credit bank account, u/s 74 of SGST Act, is unsustainable; stands lifted: HCKochi Customs seizes FC worth Rs 1.3 Cr and IC worth Rs 45 lakhsWhy Opt for IndusInd Bank Savings Account?Centre releases 13th instalment of Rs 6,000Cr to meet GST shortfallWhetting the budget (App)etiteI-T - Addition on account of revised capital gain under Sec 50C cannot be added to assessee's income, even when his revision petition is barred by limitation : HCCompensation received from municipality for cutting of trees to make way for electrical wires, forms part of assessee's trading operations where such trees were used for generating essential oils & sale thereof - Such compensation received qualifies as agri income & is non taxable: ITATMexican President is latest to test positive for CoronavirusIndia reports 13,203 fresh COVID-19 cases, 131 deathsGrant of registration & issue of assessment or exemption u/s 11 are separate & distinct & process of registration u/s 12AA cannot be made an occasion for deciding upon eligibility for exemption u/s 11: ITATAssessment order is unsustainable where based solely on third party's statements taken behind assessee's back & without permitting cross examination of the deponent: ITATCentre allocates addl Rs 660 Cr to MP for capital projectsAppeal merits re-consideration where dismissed in limine without hearing the assessee: ITATIGI Airport Customs nabs Ugandans with heroin worth Rs 68 CrCX - No reversal of Cenvat credit is warranted u/r 6(3)(b) of CCR 2004 upon removal of Spent Sulphuric Acid: CESTAT
 
Centre issues guidelines for feeder-level solarisation under PM-KUSUM Scheme

 

By TIOL News Service

NEW DELHI, DEC 04, 2020: THE Ministry of New and Renewable (MNRE) today issued guidelines for implementation of feeder-level solarisation under the PM-KUSUM scheme after consulting with state governments.

The Cabinet approved the Pradhan Mantri KisanUrja Suraksha evamUtthanMayabhiyan(PM-KUSUM) scheme of harnessing solar energy in February 2019.

The scheme has three components – Component A is installation of decentralized ground mounted grid connected renewable power plants, Component B is installation of standalone solar powered agriculture pumps and Component C is solarisation of grid-connected agriculture pumps.

“The objective of Component-C of PM-KUSUM Scheme is to provide reliable day-time power to farmers, enhancing their income by purchasing surplus solar power and thus incentivising them for saving water,” the ministry stated.

After consultation, the ministry said it has also decided to include feeder-level solarisation wherein instead of putting solar panels at each individual pump, a single solar power plant can be installed to power the agriculture feeders.

The grid connected agriculture pumps can be solarised with central and state subsidy of 30% each and farmer's contribution of 40%, the MNRE said. The solar capacity allowed is upto two times of the pump capacity in kilowatt (kW) and surplus power will be purchased by the distribution company (DISCOM).

The DISCOM or power department will be the implementing agency for feeder level solarisation in their respective areas, the guidelines state. However, states may appoint any other expert agency to help the DISCOM.

The state may also choose to install feeder level solar power plant of capacity higher than capacity required for supplying power to agriculture feeder. The additional solar power generated can be redirected to nearby rural and urban grids or stored for supplying power later in the day.

The ministry said for installation of feeder level solar power plant, Central Financial Assistance (CFA) of 30% (50% in case of northeastern states, hilly states/union territories, and islands) will be provided by the government and the balance will be met through loans from NABARD/PFC/REC.

The MNRE said that they plan to solarise 4 lakh grid-connected pumps by 2020-21 and 50% are through feeder level solarisation.