Indigenous Technology Cruise Missile successfully flight-tested by DRDO off the Odisha coastUS imposes fresh sanctions against Iranian drone productionIREDA's GIFT City office to boost Green Hydrogen and Renewable Energy Manufacturing ProjectsVoting for General Elections 2024 commences tomorrowGlobal warming up to 3 degrees to cost 10% of global GDP: StudyNexus between Election Manifesto and Budget 2024 in July!Clearing the Air: Airtel's SC Decision provides clarity on test of AgencyGST implications for Corporate Debtor under IBCI-T- Petitioner's CIBIL score lowered due to same PAN being issued to another assessee who defaulted on loan; I-T Deptt to inform CIBIL of remedial measures taken: HCBrazil’s proposal to tax super-rich globally finds many takers in G20 GroupI-T- Additions framed on account of unconfirmed cash loans upheld in part, where assessee is unable to discharge onus of proving source of cash deposits : ITATCPM manifesto promising annihilation of all weapons of mass destructions including nuclear, draws flak from Defence MinisterI-T- Registration of trust u/s 12A denied due to inadvertent error by assessee in filing Form 10AB but with wrong selection code; case remanded for reconsideration: ITATBiden favours higher steel tariff on ‘cheating’ China + may up tariff on dominant solar tech suppliersI-T- Enhancement of income is not sustainable if CIT (A) not follow sec 251 and no notice given to assessee of enhancement : ITATUS Poll: Biden trumps Trump in money race by USD 75 mnI-T- Assessee is entitled for depreciation on goodwill arising out of difference between cost of acquisition and net value of assets and liabilities as per book value of CAPL : ITATNetanyahu says Israel to decide how and when to respond to Iran’s aggressionI-T- There is no scope of extrapolation in search assessment based solely on assumptions and surmises in absence of any tangible material qua the relevant assessment year: ITATGoogle slays costs by laying off staffers & shifting roles outside USI-T- Re-assessment cannot be sustained where based on borrowed satisfaction & where conducted in a mechanical manner: ITATHeavy downpours drown Dubai; Airport issues travel advisoryCus - There cannot be an exercise of jurisdiction to injunct invocation of BG, as it is a settled principle of law that bank guarantee constitutes an independent contract between the bank and the party in whose favour BG is furnished: HCHM pledges to make India completely Maoist-freeGST - Except for holding that the taxpayer had availed ITC which is blocked credit u/s 17(5), no reasons are specified - Order set aside and matter remanded: HCMicrosoft to inject USD 1.5 bn in AI Group G42 of UAEGST - Injustice would be caused unless petitioner is provided another opportunity to contest tax demand on merits - Subject to deposit of 10% of demand, matter is remanded: HCCanadian budget proposes more taxes on higher income groups & tax credits for EVsWorld leaders appeal for quick ratification of UN Ocean Treaty
 
Rules on recovery of inter-state transmission charges notified

By TIOL News Service

NEW DELHI, OCT 03, 2021: THE Union Ministry of Power has notified the Electricity (Transmission System Planning, Development and Recovery of Inter-State Transmission Charges) Rules 2021. This paves the way for overhauling of transmission system planning, towards giving power sector utilities easier access to the electricity transmission network across the country.

At present, generating companies apply for long-term access (LTA) based on their supply tie-ups, while medium-term and short-term transmission access is acquired within the available margins. Based on LTA application, incremental transmission capacity is added. A number of sector developments, such as the increasing focus on renewable energy, and the development of the market mechanism, necessitated a review of the existing transmission planning framework based on LTA. 

The rules underpin a system of transmission access which is termed as a General Network Access in the inter-state transmission system. This provides flexibility to the States as well as the generating stations to acquire, hold and transfer transmission capacity as per their requirements. Thus, the rules will bring in rationality, responsibility and fairness in the process of transmission planning as well as its costs. In a major change from the present system of taking transmission access, power plants will not have to specify their target beneficiaries. The rules will also empower state power distribution and transmission companies to determine their transmission requirements and build them. Also, states will be able to purchase electricity from short term and medium term contracts and optimize their power purchase costs.

Apart from introducing GNA, the rules also specify clear roles of various agencies involved in the transmission planning process. The Central Electricity Authority shall prepare a short-term plan every year on rolling basis for next 5 years and perspective plan every alternative year on rolling basis for next 10 years. The Central Transmission Utility shall prepare an implementation plan for inter-State transmission system every year on rolling basis for up to next 5 years which will take into account aspects such as right –of-way and progress of the generation and demand in various parts of the country. The rules specify how the existing LTA would be transitioned into General Network Access. The rules also outline the recovery of GNA charges from the users of transmission network and assign the responsibility of billing, collection and disbursement of inter state transmission charges to the Central Transmission Utility.

The rules have enabled, for the first time, that the transmission capacity can be sold, shared or purchased by the States and generators. The rules prescribe that excess drawal or injection over the GNA capacity sanctioned shall be charged at rates which are at least 25% higher and this will ensure that the entities do not under-declare their GNA capacity. The Central Electricity Regulatory Commission (CERC) has been empowered to bring out detailed regulations on GNA in inter state transmission system.

The Central Government has notified these rules with a view to streamline the process of planning, development and recovery of investment in the transmission system.  The rules are aimed at encouraging investments in the generation and transmission sectors. The rules will enable the country to develop deeper markets.

Transmission system is the vital linkage in the power sector value chain connecting the generation and the demand. The Central Government is committed towards ensuring adequacy of transmission system for supply of power from one State to another State and across regions.  The Rules brought out by the Central Government underpin that “electricity transmission planning shall be made in such way that the lack of availability of the transmission system does not act as a brake on the growth of different regions and the transmission system shall, as far as possible, to be planned and developed matching with growth of generation and load and while doing the planning, care shall be taken that there is no wasteful investment”.

In a series of other reforms carried out earlier, also on the directions of the Union Power Minister, Shri R. K. Singh, the Ministry had separated the Central Transmission Utility from POWERGRID to provide transparency and a level playing field in the bids for transmission and reduced the lock-in period for transmission projects in order to attract investments and more competition. The Ministry of Power also issued the Right of Consumer rules, which empower consumers and rules laying down the ceiling for late payment surcharge.


POST YOUR COMMENTS
   

TIOL Tube Latest

Shri N K Singh, recipient of TIOL FISCAL HERITAGE AWARD 2023, delivering his acceptance speech at Fiscal Awards event held on April 6, 2024 at Taj Mahal Hotel, New Delhi.




Shri Ram Nath Kovind, Hon'ble 14th President of India, addressing the gathering at TIOL Special Awards event.