How To ServeImpeached South Korean President Yoon finally arrestedI-T- Re-assessment order valid where assessee fails to explain nature & source of certain income disclosed in course of Search operations: HCUS SEC sues Musk over delays in disclosure of Twitter purchaseI-T - Entire purchases can't be disallowed if AO never doubted production & sales, merely because ITC availed on purchases made by assessee was not admissible and assessee had paid tax under VAT Act: HCBiden’s farewell shot: No import of Chinese vehiclesI-T - If AO had not made specific allegation that assessee had paid money through banking channel and received back cash against those payments, then matter shall be remanded to AO to consider afresh: HCUS House okays Bill banning transgender athletes from women’s sportsI-T - No tax can be levied on advance amount received by assessee for agreed sale proceeds, if no sale of land was actually executed during year under consideration: ITATMeta to lay off 5% of poor performersI-T - 'Shastras & scriputres' define only way of life of civilized society and they are definitely not religion specific for benefit of public at large, and hence no reason to deny exemption u/s 80G(5) to trust: ITATGaza ceasefire deal likely to be lockedI-T- When new flat is obtained on transfer of old flat, assessee's claim for deduction u/s 54 of the Act is justified: ITATGovt appoints Justice D K Upadhyaya as CJ of Delhi HC & Justice Alok Araddhe as CJ of Bombay HCCoal imports drop by 3.1% during April-October, 2024VAT - Assessment order passed on estimate basis is upheld where assessee does not maintain accurate records or books of accounts: HCPoK is nothing more than foreign territory to Pakistan: RMCus - Delays be dealt with liberally, especially when there is no deliberate attempt to delay filing of refund claims; rejecting refund claims on technical grounds of limitation, is not tenable: CESTATPM launches 'Mission Mausam', releases IMD Vision-2047 documentCX - Assessment order passed without granting personal hearing; assessee's difficulties in participating in adjudication due to COVID pandemic overlooked - case remanded: CESTATMNRE issues Guidelines for implementation of PM-Surya GharCX - Rejection of assessee's refund claims without issuing a Show cause notice or giving valid reasons for rejecting claims, contravenes principles of natural justice: CESTAT
 
4 major projects operationalized in UP and Bihar under Namami Gange Mission 2.0

 

By TIOL News Service

NEW DELHI, AUG 07, 2024: IN a significant stride towards rejuvenating and conserving the sacred River Ganga, the Government of India has successfully completed and operationalized four major projects under the Namami Gange Mission 2.0 in the first quarter of fiscal year 2024-25. These initiatives located across the mainstream of the river Ganga in Bihar and Uttar Pradesh, are pivotal in the ongoing efforts to curb pollution and enhance the ecological health of the Ganga and its tributaries.

These projects built for Rs. 920 crores, will add 145 MLD of sewage treatment capacity, provide better sewer networks, and intercept numerous drains. Designed to meet the stringent discharge standards prescribed by the National Green Tribunal, these initiatives ensure substantial improvements in the water quality of the Ganga and its tributaries.

The project at Munger (Bihar) will improve sewer network, and establish Sewerage Treatment Plant (STP) at an estimated cost of Rs. 366 crores. This comprehensive project involves the development of a 175 km sewerage network and the construction of a 30 MLD capacity STP. The project has been implemented using the DBOT (Design, Build, Operate, and Transfer) Model. It will benefit approximately 3,00,000 residents by connecting their households to the sewer network, significantly improving the city's sanitation infrastructure and preventing the discharge of untreated sewage into the River Ganga.

The other important project, established at Mirzapur (Uttar Pradesh) is for the Interception, Diversion and Treatment Works for abatement of Pollution of River Ganga . This project, built at an estimated cost of Rs. 129 crores, is now operational and focuses on the abatement of pollution in the Ganga at Mirzapur by intercepting nine drains and rehabilitating six existing drain interception structures. With the inception of two new STPs-Pakka Pokhra and Bisunderpur-each with a capacity of 8.5 MLD, along with the rehabilitation of existing STPs, the sewage treatment capacity has now increased to 31 MLD. This project prevents untreated sewage from entering the Ganga, significantly improving water quality and supporting aquatic biodiversity.

The project in Ghazipur (Uttar Pradesh) has been established for interception, diversion, and treatment works for abatement of pollution of River Ganga , with a sanctioned cost of Rs. 153 crores. This project, now operational, includes the development of a 1.3 KM I&D network and 21 MLD STP. This project benefits city by treating sewage effectively, preventing the discharge of untreated sewage into the Ganga.

Apart from Mirzapur and Ghazipur, an important project for interception, diversion, and sewage treatment works has been established at Bareilly (Uttar Pradesh) at an estimated cost of Rs. 271 crores and is now operational. This project targets pollution abatement in the river. It includes the interception and diversion of 15 drains and the construction of three STPs with a combined capacity of 63 MLD. The Project will benefit the city by having its sewage treated at the STPs and thereby avoiding discharge of untreated sewage to river Ramganga, resulting in the improvement in the water quality of the river Ganga.

These projects based on Hybrid Annuity PPP (HAM) model have been designed on the basis of Advanced Sequencing Batch Reactor technology. The STP's have been meticulously constructed in accordance with the strict standards and guidelines set by the National Green Tribunal (NGT). These projects, along with giving a boost to the Namami Gange mission by treating wastewater and making the rivers clean, will also benefit a large population of the respective cities.

Through the National Mission for Clean Ganga (NMCG), the Government of India remains unwavering in its commitment to the holistic rejuvenation of the Ganga. These projects stand as a testament to the Prime Minister Shri Narendra Modi led government's dedication to create a cleaner, healthier and more vibrant river ecosystem for future generations.