News Update

Undervaluation of Imported Aluminium Scrap (Part 3 of series)Indian solar suppliers substitute tossed out Chinese players in US supply linePrivacy in Peril: Have We Forgotten Our Rights?New Trumpian threat: 200% tariff on vehicles imported from MexicoI-T- Writ petition filed before exercising option of rectification petition, is premature: HCRG Kar case: 10 Docs aligned to former Principal tossed out of hospitalI-T- If at all there is some disallowance/adjustment in a year, same should be adjusted with the available brought forward business loss of the assessee: ITATMedical emergency: London-heading Air India flight stops over in DenmarkSales Tax - Benefits from exchange rate fluctuations do not transform receipts therefrom into something other than taxable turnover: HCJaishankar says AI can be as fatal to world as N-weaponsCus -SAD refund - Date of making refund application would be required to be considered from date of final assessment and not from date of payment of provisional duty: HCTraumatised by Helene, Florida laces up for major hurricane MiltonGST - Non-payment of dues for a period of three months is not a prescribed ground u/s 29 and/or u/r 21 for cancelling the petitioner's GST registration: HCChinese hackers hack into US court-sanctioned wiretapping serverGST - Notices issued to an assessee, who is no more and assessment orders passed based on such notices are void ab initio and liable to be set aside: HC10 children drown in Bihar; CM announces Rs 4 lakh ex-gratia paymentGST - Cancellation of registration is invalidated where specific reason as to alleged fraud, wilful misstatement or suppression of facts is not stated in Show Cause Notice & no further information is given to justify such action: HCDrugs & raw materials worth Rs 1800 Cr seized in Bhopal; Two arrestedDRDO successfully flight-tests 4th Generation Air Defence System7 of a Mumbai family suffocate to death after short-circuit sparks fireCus - In absence of evidence to establish that appellant was aware of presence of branded products in consignment when bills were filled, goods are not liable for confiscation and no penalty under section 112 of Customs Act, 1962 can be imposedNew Zealand naval ship sinks off Samoa; 75 onboard rescuedChennai Metro Rail Project Phase 2: Centre to finance 65 per cent of costNavin Jindal goes on horseback to cast vote in HaryanaCX - Assessee eligible for self-credit of taxes paid in past periods, where conditions in Notification No. 20/2007-CE, as amended by Notification No. 20/2008-CE are satisfied: CESTATIndia’s forex kitty surpasses USD 700 bn for first timeIndian delegation, led by Meghwal, visits United KingdomST - Sale of immovable property is excluded from definition of service u/s 65B(44) of Finance Act, 1994; Such exclusion aligns with Constitutional mandate under Article 366(29) & cannot be deemed to be validly legislated rule in light of Section 38A of the Central Excise Act, which applies to Service Tax matters: CESTATBy 2047 India to be world largest economy: Dr Jitendra SinghST - Construction of residential complex service - Assessee's claim for refund of tax paid rightly denied on grounds of unjust enrichment, where assessee passed tax incidence onto consumers: CESTATPlans unveiled for Indian Maritime Heritage Conclave in Dec 2024Cus - Penalty imposed on CHA on allegations of clandestine clearance of imported goods, is not tenable, where no evidence exists to establish CHA's role in improper removal of goods: CESTAT
 
Chennai Metro Rail Project Phase 2: Centre to finance 65 per cent of cost

By TIOL News Service

NEW DELHI, OCT 07, 2024: THE Union Cabinet approved the Chennai Metro Rail Project Phase 2 as the 'Central sector' project recently at a total estimated cost of Rs. 63,246 crore.

So far, the project was being implemented as a 'State sector' project with responsibility of the project financing being primarily on the Government of Tamil Nadu to the extent of almost 90 per cent of the estimated project cost. The role of the Central Government was to finance 10 per cent of the project cost, excluding land cost and few other items as per the Metro Rail Policy 2017. However, the Central Government had also assisted the State Government in mobilisation of Rs. 32,548 crore as loans from bilateral and multilateral agencies to the State Government directly, out of which around Rs. 6,100 crore has been utilised so far.   

With the recent approval, the Central Government now will be financing almost 65 per cent of the estimated cost of Chennai Metro Phase 2.  This financing will include the entire required loan of Rs. 33,593 crore besides the equity and subordinate debt of Rs. 7,425 crore.

The balance 35 per cent of the estimated cost will be financed by the State Government.

The loans taken from multilateral and bilateral development agencies will be treated as the loans to the Central Government and will be provided directly to Chennai Metro Rail Limited (CMRL) from the Central Government's budget.

Before approval of the project by the Centre, the responsibility of providing or arranging the loan financing for the project was on the State Government.

The Union Cabinet's approval has freed up budgetary resources of the State Government to finance other development activities to an extent of Rs. 33,593 crore.

In pursuance of the Union Cabinet's approval, the Ministry of Finance will be approaching the bilateral and multilateral agencies, namely Japan International Cooperation Agency, Asian Development Bank, Asian Infrastructure Investment Bank and New Development Bank for renegotiating the loan and project agreements and related documents for:

1. treating the loans as the loans to the Central Government and not to the State Government,

2. changing the loan flow route from the respective agency to the Central Government and from the Central Government's budget to CMRL directly as the pass-through assistance, in place of the existing route of the flow being from the respective agency to the State Government and from the State Government's budget to CMRL,  

3. designating Ministry of Housing & Urban Affairs acting through CMRL being the project executing agency in place of the State Government through CMRL being the project executing agency.

The process for these changes to the loan and project agreements and the related documents has been initiated, and will be completed expeditiously in coordination with the State Government.

The responsibility of repayment of the loan will be on the company.  The repayment would normally start after a moratorium of at least five years, i.e., more or less after completion of the project. In the event of CMRL not being in a position to repay the loan, it would be the obligation of the State Government to provide financial support to the company to enable the repayment in those years.


POST YOUR COMMENTS
   